Select Currency
Translate this page

EMPIRICAL DETERMINATION OF LABOUR OUTPUTS FOR BLOCK LAYING

Format: MS WORD  |  Chapter: 1-5  |  Pages: 75  |  2495 Users found this project useful  |  Price NGN5,000

  DOWNLOAD THE FULL PROJECT

EMPIRICAL DETERMINATION OF LABOUR OUTPUTS FOR BLOCK LAYING

 

ABSTRACT

The source and nature of output constants used for preparation of construction estimates should be accurate and reliable for the client to have confidence on the prepared estimates. This research is focused on using time study approach to empirically determine the outputs of block laying work items inconstruction industry. The study reviewed BESMM3 and surveyed possible block work items in construction sites. Ten work items were selected from the identified block work items in BESMM3 and construction sites for Physical observations and output measurement. A total of 105 sites were observed in F.C.T., Abuja and Nasarawa state. Data collected were subjected to statistical analysis using both the descriptive and inferential data analysis techniques. The inferential tools adopted were T-test and ANOVA statistics to assess and examine the influence of some selected labour productivity factors on the outputs of the workers observed. The inferential test revealed the following; period of observation, shape of the building and mode of employment significantly affected outputs on the ten work items. The results of the analysis carried out established mean output values per day for: 150mm thick block in foundation (12.85m2); 150mm thick block in superstructure (13.22 m2); 150mm thick block in superstructure overhand (12.47m2); 225mm thick block in foundation (8.90m2); 225mm thick block in superstructure (11.17m2); 225mm thick block in superstructure overhand (9.16m2); 225mm thick block isolated piers in superstructure (5.00m2); 225mm thick block piers in superstructure overhand (4.57m2); 225mm thick block in pit bottom plan > 4 m2(7.85m2); 225mm thick block in bottom plan < 4 m2 (7.13m2). The study also identified forty-four (44) block work items not captured in BESMM3 and suggested that these work items be incorporated into BESMM3 for productive and cost implication. The research recommended that in compliance to BESMM3, the NIQS in collaboration with NJIC to sponsor a research on determination of labour outputs in all trades as a way to ensure uniformity in output constants. The study therefore finally concludes that SMM takes cognizance of productivity impact associated with labour and it is imperative for reliability and accuracy in block work estimate to empirically determine labour outputs on the basis of work items as stated in BESMM3.

 

CHAPTER ONE

INTRODUCTION

1.1   Background of the Study

In Nigeria, like most developing countries, the construction industry plays a dominant role in the economic activities of the country.The efficiency of the construction industry has been established to heavily rely on its level of productivity. Construction productivity is constantly declining over a decade due to the lack of standard productivity data base system and ignorance of impact of various factors influencing labour productivity (Muqeemet al., 2011).The accuracy of the project cost estimates depend largely on the degree of accuracy of cost information obtained on the key components of an estimate (i.e. labour, plant, material, and profit and overhead) (Abdullahi, 2009), while the use of Standard Methods of Measurement (SMM) for the preparation of BOQ gives the quality and standard of the extent of work to be done, it also takes precedence of the cost significances of every classes of operations within a trade.

The common method of generating cost estimates for construction projects involves the multiplication of unit rate by the measured quantities in the bill of quantities (Ashworth, 2002).The unit rate is a component of labour rate (obtained from the multiplication of labour constant by all-in rate) plus cost of material and percentage allowance for profit and overhead, while the measured quantities are obtained from drawings and specifications for the works rules specified by Building and Engineering Standard Methods of Measurement (BESMM3). RISK IDENTIFICATION AND ASSESSMENT IN HOUSING DEVELOPMENT PROJECTS USING ANALYTICAL HIERARCHICAL PROCESS.

  DOWNLOAD THE FULL PROJECT

EMPIRICAL DETERMINATION OF LABOUR OUTPUTS FOR BLOCK LAYING

Not The Topic You Are Looking For?



For Quick Help Chat with Us Now!

+234 813 292 6373

+233 55 397 8005


HOW TO GET THE COMPLETE PROJECT ON EMPIRICAL DETERMINATION OF LABOUR OUTPUTS FOR BLOCK LAYING INSTANTLY

  • Click on the Download Button above.
  • Select any option to get the complete project immediately.
  • Chat with Our Instant Help Desk on +234 813 292 6373 for further assistance.
  • All projects on our website are well researched by professionals with high level of professionalism.

Here's what our amazing customers are saying

Gbadamosi Solomon Oluwabunmi
Lasu
Swift delivery within 9 minutes of payment. Thank you project master
Excellent
Samuel From Ajayi Crowther University
You guys just made life easier for students. Thanks alot iprojectmaster.com
Excellent
Emmanuel Essential
Kogi state University
I actually took the risk,you know first time stuff But i was suprised i received as requested. I love you guys 🌟 🌟 🌟 🌟
Very Good
Peace From Unilag
I cried not knowing how to go about my project but the day i searched online and saw iprojectmaster, i called and got my full project in less than 15minutes, i was shocked!
Excellent
Adam Alhassan Yakubu
UDS
Excellent work and delivery , I promise to share my testimonies everyone in need of this kind of work. You're the best
Excellent
MATTHEW NGBEDE
Ahmadu Bello University
I wish I knew you guys when I wrote my first degree project, it took so much time and effort then. Now, with just a click of a button, I got my complete project in less than 15 minutes. You guys are too amazing!
Excellent
Joseph M. Yohanna
Thanks a lot, am really grateful and will surely tell my friends about your website.
Excellent
Azeez Abiodun
Moshood Abiola polytechnic
I actually googled and saw about iproject master, copied the number and contacted them through WhatsApp to ask for the availability of the material and to my luck they have it. So there was a delay with the project due to the covid19 pandemic. I was really scared before making the payment cause I’ve been scammed twice, they attended so well to me and that made me trust the process and made the payment and provided them with proof, I got my material in less than 10minutes
Very Good
Oluchi From Michael Opara University
If you are a student and you have not used iprojectmaster materials, you are missing big time! iprojectmaster is the BEST
Excellent
Musa From Ahmadu Bello University
Thank you iprojectmaster for saving my life, please keep it up and may God continue to bless you people.
Excellent

FREQUENTLY ASKED QUESTIONS

How do I get this complete project on EMPIRICAL DETERMINATION OF LABOUR OUTPUTS FOR BLOCK LAYING?

Simply click on the Download button above and follow the procedure stated.

I have a fresh topic that is not on your website. How do I go about it?

How fast can I get this complete project on EMPIRICAL DETERMINATION OF LABOUR OUTPUTS FOR BLOCK LAYING?

Within 15 minutes if you want this exact project topic without adjustment

Is it a complete research project or just materials?

It is a Complete Research Project i.e Chapters 1-5, Abstract, Table of Contents, Full References, Questionnaires / Secondary Data

What if I want to change the case study for EMPIRICAL DETERMINATION OF LABOUR OUTPUTS FOR BLOCK LAYING, What do i do?

Chat with Our Instant Help Desk Now: +234 813 292 6373 and you will be responded to immediately

How will I get my complete project?

Your Complete Project Material will be sent to your Email Address in Ms Word document format

Can I get my Complete Project through WhatsApp?

Yes! We can send your Complete Research Project to your WhatsApp Number

What if my Project Supervisor made some changes to a topic i picked from your website?

Call Our Instant Help Desk Now: +234 813 292 6373 and you will be responded to immediately

Do you assist students with Assignment and Project Proposal?

Yes! Call Our Instant Help Desk Now: +234 813 292 6373 and you will be responded to immediately

What if i do not have any project topic idea at all?

Smiles! We've Got You Covered. Chat with us on WhatsApp Now to Get Instant Help: +234 813 292 6373

How can i trust this site?

We are well aware of fraudulent activities that have been happening on the internet. It is regrettable, but hopefully declining. However, we wish to reinstate to our esteemed clients that we are genuine and duly registered with the Corporate Affairs Commission as "PRIMEDGE TECHNOLOGY". This site runs on Secure Sockets Layer (SSL), therefore all transactions on this site are HIGHLY secure and safe!